South Auckland Hospital buildings full of rot and mould

Report warns against risks to patients and staff

Radio New Zealand

Auckland, March 22, 2018

Four big Middlemore Hospital buildings that serve thousands of South Auckland people are full of rot and dangerous mould that could make staff and patients sick.

The rotten buildings include the children’s hospital and the Manukau Super Clinic and new documents show that the decay is so bad it is in danger of breaching the walls and contaminating the air.

The Counties Manukau District Health Board faces a repair bill of tens of millions of dollars but says that patient safety is not compromised so long as the fungal spores stay in the walls.

The documents also show that the hospital’s management have known for years the buildings were leaking but had not fixed them.

Independent Investigation

The information obtained under the Official Information Act includes an independent investigation report.

It has found significant fungus and bacteria inside the walls of four buildings – brown rot, fungus and Stachybotrys in multiple places.

Exposure to Stachybotrys can cause severe illness.

About 90% of the timber framing looked at in the Kidz First hospital is decaying, the wood soaked at up to 98% moisture levels.

“The timeframes for repair are critical as the moisture damage of these buildings is in places close to breaching the internal linings,” the report to the District Health Board by surveyors Alexander and Co, said.

Ad-hoc repairs risky

“Ad-hoc emergency repairs are unlikely to be an acceptable option as they present a risk to patients and staff and will adversely affect the smooth operation of the facility.”

If any walls were breached, it would have to vacate those areas, the Counties Manukau DHB acting chief executive Gloria Johnson said in a report to RNZ accompanying the OIA response.

“At this time, clinical expert advice is that provided the wall spaces are not open to ventilation into the hospital, or near to an air intake, patient safety is not compromised by the fungal growth found,” she said.

The other “real” risk at all four buildings is the cladding will fall off and hit someone as fixings into the rotten frames fail.

It is understood that a two square metre piece of heavy cladding fell off the Scott Building in 2012, which first raised the alarm about the leaks.

Three facilities compromised

Three major buildings at Middlemore Hospital at Otahuhu are compromised: the Kidz First Hospital, the Scott and McIndoe Buildings; and the big Super Clinic, located about 8 kms South in Manukau.

The Scott building includes medical, surgical and wards for elderly people; McIndoe has the National Burns Centre, and intensive care; Kidz First includes acute care for children with breathing difficulties and a neonatal unit.

Huge turnover

Middlemore alone handles 91,000 patients and 350,000 outpatients a year, with almost 5000 staff.

“In a few locations to the Kidz First Building and the Super Clinic Complex, the inner face of the plasterboard linings had been affected by fungal growth and this damage will readily transfer to the interior of the building in the short to medium term,” the investigation report said.

The DHB wants to do all the repairs while everything is kept running.

“The key issue is the need for this to be undertaken with the buildings fully operational as an acute hospital facility,” Ms Johnson said.

Only the McIndoe building has had much remedial work done on it – but its ambulance bay is one of the worst spots of all, with a “high” risk that cladding would fall off.

All four buildings were constructed between 1999 and 2001, in the heyday of the leaky building crisis, before law changes in 2004 banned the use of untreated timber framing in walls.

The other factor to the four leaky buildings was “shortfalls in build methods”, the DHB said.

The major construction firm Hawkins both designed and built all four buildings, it said.

Court action

The OIA reveals that the DHB took an offshoot of Hawkins, Hawkins Construction North Island Ltd – now called H Construction North Island Limited – to court in 2012.

It reached a full and final settlement only a year ago. The board won’t reveal the amount, saying this was confidential, even under the OIA.

The DHB has awarded that repair contract to Hawkins, the firm it sued over the Scott building.

The Hospital first knew back in 2012 there was a problem at Kidz First and the Scott Building; it was a year or two later it found out about the others.

In 2015 the board started getting reports, the OIA showed. The board is refusing to release the minutes of any of those meetings to RNZ, citing commercial, government and negotiation grounds.

Gloria Johnson got the Alexander and Co report in November last year.

Risk Certain and Extreme

An internal DHB report just 2 weeks ago rated the corporate risk to the DHB “certain” and “extreme”.

The investigator recommended (a) Barriers to keep people out of areas where cladding might fall on them outside (b) That air quality testing inside may be necessary; and (c) And monitoring of the wall linings inside.

It is unclear if all or any of that is happening. The Chief Executive notes only that safety monitoring measures are in place at the Scott building.

As for an overall fix, the OIA response shows multi-million-dollar overhauls are now urgently needed.

“We understand that at least some patients and staff will have a low resistance to mould- contaminated building materials affecting the air quality. This factor alone may impact on the required urgency and timing of the repairs,” Alexander and Co said.

Four-Year Project

But fixing the cladding is not scheduled to begin till July this year and will not be finished until 2022.

Even at the worst-hit building, the Scott building, only the design phase has started.

The OIA response suggests the hospital hasn’t yet hit on a way of doing the work, while safeguarding patients and staff and staying fully operational as an acute hospital.

South Auckland’s health board is not saying what safety measures it has put in place at the four major hospital buildings with dangerous rot and mould in their walls.

The Counties Manukau DHB says that monitoring is on place at one of the buildings, but it is not giving any details.

Indian Newslink has published the above Report and Pictures under a Special Agreement with www.rnz.co.nz

*

Photo Caption:

  1. The Middlemore Hospital main building in Otahuhu (RNZ picture by Claire Eastham-Farrelly)
  2. Chart of buildings decay (Supplied to RNZ)

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Share this story

Related Stories

Indian Newslink

Advertisement

Previous slide
Next slide

Advertisement

Previous slide
Next slide

Advertisement

Previous slide
Next slide

Advertisement

Previous slide
Next slide

Advertisement

Previous slide
Next slide

Advertisement

Previous slide
Next slide

Advertisement

Previous slide
Next slide

Advertisement

Previous slide
Next slide

Advertisement

Previous slide
Next slide